Hail repair update

19 Oct 2023

Menzies Library 

  • Roofing repairs are progressing well, with the upper roof nearly complete. Images of the progress are available in the slideshow above. 
  • As part of the roof remediation works replacement there will also be replacement of damaged carpet areas on Level 2. The replacement activities will take place in late November/December. 

Law Library 

  • Following damaging storms, Level 2 has been fully closed. If you need books from Level 2, please submit a retrieval request. 
  • Waterproofing membrane will be fully laid down by next week. Copper will be installed from Monday 23 October and will likely take a few weeks to be completed. 
  • Scoping work has commenced to determine the extent of carpet replacement. 
  • Discussions are being held to determine if additional student spaces can be made accessible within the Law building. 

Art & Music Library 

  • It is likely the Library building closure will take place in December. We will provide further updates as details are finalised. 

Visit the hail repair updates webpage for more information about upcoming works. 

Please get in touch with Library staff if you have any questions or concerns.