Hi all,
Notes below from the meeting on Wednesday.
- Hip end on the South West corner left. Scheduled to be completed early next week.
- 95% of the top metal roof section complete.
- A. Corazzon to liaise with Vanessa regarding staff access to level 4 starting next week.
- A crane is booked for Saturday 18/Feb assist with removing final metal roofing materials.
- CC to liaise with carpenters regarding potential installation time for the ceiling tiles.
Regards,
Andrea Corazzon
Construction Control