Law Library – hail update

29 Feb 2024

Hail remediation works in the Law Library are on track, with no delays expected. Updates on specific works are below. 

  • Ceiling tiles are being installed on level 2. 
  • Asbestos removal on 17 February was completed. 
  • The returns chute may need to be closed while work is undertaken on the library entrance – we will provide an update here when details are confirmed. 
  • Scaffolding will be installed on 1 March around the Moot Court entrance. Safety crew will be in place to stop foot traffic, and we advise you use other entrances. 
  • The work in Whitmore Walk is completed. 
  • The roofing membrane is on above the theatre and café entrance.

Thank you for your patience during this process. 

If you have any questions, please get in touch with our helpful library staff.